Previous revision
log [2024/06/01 11:51] – [Activities] team5log [2024/06/13 11:03] (current) – [15th Week Report] team5
Line 75: Line 75:
 Our questions about the prototype were answered. In the area of media design, we started with the user manual and made initial considerations regarding the promotional video. Our questions about the prototype were answered. In the area of media design, we started with the user manual and made initial considerations regarding the promotional video.
 ==== 13th Week Report ==== ==== 13th Week Report ====
-//Fill in with a short description of your activities during this week// +This week we finished the functional tests on the software. 
 +We started making the prototype on Friday, but it's not finished yet. And we proceeded to make the user manual. 
 +On the weekend we finished the paper.
 ==== 14th Week Report ==== ==== 14th Week Report ====
-//Fill in with a short description of your activities during this week// 
  
 +This week, the team worked on the prototype. The wooden and acrylic parts have been constructed separately, and the electronic part functions.
 +Regarding the paper, it was reviewed and the stress analysis was implemented. 
 ==== 15th Week Report ==== ==== 15th Week Report ====
-//Fill in with a short description of your activities during this week// +This week the video was filmed and edited together. The prototype is finished with all the electrical components in there.  
 +The presentation was made and all information was gathered. We made some final changes in the wiki, like putting in some extra references, add information about the app,...
  
  
Line 225: Line 227:
  
 === Minute: === === Minute: ===
-Meeting leader: Colin +Meeting leader: Colin \\ 
-//To be added by the team.//+We discussed the possibilities for engagements for SMASHY such as stickers, the educational component. Finally we said we're going to make an app and it's possible to connect by scanning an NFC reader with a phone. 
 +We didn't got reaction from the town hall, because the supervisor first want us to have one specific idea that they can present. 
 +There was some feedback on our report, for example where to write table, figure, references and the layout 
  
 ==== 10th Meeting  (2024-05-02) ==== ==== 10th Meeting  (2024-05-02) ====
Line 281: Line 286:
 === Agenda: === === Agenda: ===
  
 +  * feedback on the marketing (paper) 
 +        * should we add another marketing strategy example?
 +
 +  * Prototype: glue it and cover it with the stickers or rebend another acrylic plate?
 +  * NFC tag
 + 
 === Minute: === === Minute: ===
-//To be added by the team.//+Meeting leader: Selma
  
 +During the meeting, the team asked for feedback on the marketing subchapter for the paper and will receive feedback shortly. Some refinements for the paper were pointed out to work in the next few days. 
 +Regarding the prototype, some stickers were proposed to solve the visible breakage on the acrylic plate. Also, the team got the confirmation that the LEDs can be glued. 
 ==== 15th Meeting  (2024-06-13) ==== ==== 15th Meeting  (2024-06-13) ====
  
 === Agenda: === === Agenda: ===
 +  * What should be in the final presentation? 
 +  * When presentation uploaded?
 +  * How to upload the code?
  
 === Minute: === === Minute: ===
 +Leader of meeting: Mats\\
  
-//To be added by the team.//+We discussed what should be in the presentation, the supervisor gave us a good oversight of everything. 
 +Everything should be uploaded by Sunday. 
 +The code needs to be uploaded on github or a similar site.
 ===== Activities ===== ===== Activities =====
-//Please register here all accomplished project activities// 
- 
 ^ Start      ^ End       ^ Task          ^Description ^  Who^ ^ Start      ^ End       ^ Task          ^Description ^  Who^
 |22/02/2024 | 24/02/2024 |Chose a top 3 of the list proposals |Everyone voted a top 3 himself and afterwards we put in together for a general top 3 Whole team| |22/02/2024 | 24/02/2024 |Chose a top 3 of the list proposals |Everyone voted a top 3 himself and afterwards we put in together for a general top 3 Whole team|
Line 319: Line 336:
 | 23/05/2024 | 05/06/2024  |Manual  | Making a manual on how to play the game and how to install the module. | FH, MG and JdV | | 23/05/2024 | 05/06/2024  |Manual  | Making a manual on how to play the game and how to install the module. | FH, MG and JdV |
 | 31/05/2024 | 05/06/2024  |Making prototype  | Making the physical prototype and adding the components to it. | FH, MG and JdV | | 31/05/2024 | 05/06/2024  |Making prototype  | Making the physical prototype and adding the components to it. | FH, MG and JdV |
 +| 10/06/2024 | 15/06/2024  |Video  | Making a video promoting our product and telling the project development. | MD, MG and CH |
 +| 08/06/2024 | 17/06/2024  |Presentation   | Change the presentation from interim presentation to final presentation  | Whole team |
  
  
  • log.1717239089.txt.gz